ICSS S.p.A.: photovoltaic plant work progress
The installation work of the photovoltaic system on the industrial roof of ICSS S.p.A. is proceeding according to the pre-established programmes. in the production plant of Gropello Cairoli (PV).
The consolidation operations of the support structure have been completed. At the same time, the installation of the first Jinko Solar photovoltaic modules began. Once the work is completed, this plant will include 711 545-watt modules and 3 100-ktl Growatt inverters.
As can be seen from the photos below, in order to limit the operation times as much as possible, the Inveco technical staff is specifically trained to use the latest generation lifting equipment.
According to the programs, the installation will be completed within the month of April. With this plant equipment, the customer will achieve energy autonomy of around 20%.
The contract involves the construction of a photovoltaic system with a nominal power of 387 kW, perfectly integrated with the industrial roof.
Updates will follow at the end of the works from the Gropello Cairoli (PV) plant.