Modulo srl: plant completed and operational

In the first days of October the installation of the MODULO384 photovoltaic system was completed, the overall duration of the same was equal to 80 days, a period during which an average of 8 people worked a day. On 10 October, the plant was successfully connected to the ENEL network, and from the 15th the …

Leonardo Corbucci News

Dayco Europe Srl – San Bernardo D’Ivrea

Maintenance work continues as planned in the Dayco Europe Srl plant in San Bernardo d’Ivrea (TO). The aforementioned works concerned the north wall with asbestos disposal operations on the facades and restoration of the same with sandwich tiles in line with the architectural constraints of the MAAM of Ivrea (open-air museum of modern architecture). The …

Leonardo Corbucci News

Module srl: work progress – Step 2

The assembly activities of the Jinko Solar photovoltaic modules, MODULO364 photovoltaic system, began this morning. According to the planning shared with our suppliers, the assembly of the modules on all roofs should be completed by 10 September. In the images you are seeing we also highlight the assembly of the anchoring weights of the aluminum …

Leonardo Corbucci News

Module srl: work progress

During the week of August 15th, the installation work of the MODULO364 photovoltaic system continues unabated. According to the planning shared with our suppliers, the activities could end at the end of September 2 months in advance of the contract and with the plant going into operation as early as next October. In the images …

Leonardo Corbucci News

Modulo srl: start of works and Crowdfunding campaign

The installation works for the 384 kw photovoltaic system at the Umbertide (PG) plant of Modulo Srl are proceeding rapidly. The ambitious work schedule envisages the construction of the 4 photovoltaic fields by next autumn and entry into operation in the first decade of December. Work progress to date sees all the lifelines of the …