Five new energy efficiency projects completed!
The work of five new orders has been completed, who have trusted us and entrusted their important investments in a green key and energy efficiency.
We can say with some pride that we have completed five new orders, on schedule and with the best results.
Below we report the main information of our projects, also indicating how the future of these five customers will be decidedly greener, after the installation of the systems.
ICSS SpA
The contract involved the construction of a photovoltaic system with a nominal power of 387 kW, perfectly integrated with the industrial roof of the Gropello Cairoli (PV) plant.
On this plant we installed 711 Jinko Solar modules of 545 watts and 3 Growatt inverters of 100 ktl.
The installation was completed in April. With this plant equipment, the customer has achieved an energy autonomy of about 20%.
SCATOLIFICIO SAICO Srl
The contract involved the construction of a photovoltaic system with a nominal power of 245 kW, integrated into the industrial roof of the Promano (PG) plant.
On this plant we installed 434 Jinko Solar modules of 565 watts and 2 Growatt inverters of 100 ktl.
The customer had adhered to the Umbrian Regional Tender "Solar Attack" and the system was installed in March. With this plant equipment, the customer has achieved an energy autonomy of more than 40%.
WORKMEC SpA
The contract involved the construction of a photovoltaic system with a nominal power of 188 kW, integrated with the industrial roof of the Busnago (MB) plant.
334 Jinko Solar modules of 565 watts and 2 Growatt inverters of 100 ktl were installed on this plant.
In March, the customer carried out major maintenance on the industrial roofing, disposing of the asbestos encapsulated under the current sheets and a complete 360-degree restoration. In April, however, we intervened with the installation of our system.
Unlike the other customers, WORKMEC has opted for a 12-year plant lease contract with the option to purchase or renew the lease at the end of the period.
We have paid some attention to every detail of the supply chain, from the design of the basket, to the development of the finished product, to the optimization of the packaging.
FERROTRAMVIARIA SpA
The contract involved the construction of a photovoltaic system with a nominal power of 140 kW.
248 Jinko Solar modules of 565 watts and 1 Huawei inverter of 100 ktl were installed on this plant.
According to the program shared with the customer, the installation was made above the sheds of the Bari railway junction, a strategic site for the maintenance of railway carriages. The plant was built in March and allows the customer more than 30% energy independence.
HOTEL GARDENIA IVREA
Finally, last but not least, a complete 360° installation, a mix of photovoltaic storage system and car charging stations.
The contract involved the construction of a photovoltaic system with a nominal power of 40 kW, using 72 Jinko Solar modules of 565 watts, a 30 kW Huawei Luna2000 integrated storage system, 3 Huawei inverters of 10 ktl and 3 ABB wallbox columns of 22 kW .
The works were completed in the first ten days of March and with this plant equipment Hotel Gardenia has achieved an energy autonomy (system + storage) of more than 60%.