Scatolificio SAICO s.r.l.: progress of the photovoltaic plant works
The installation work of the 245 kW photovoltaic system that we are preparing on the industrial roof of our customer Saico S.r.l at the Coldipozzo (PG) plant is continuing rapidly.
Our program calls for the plant to be fully installed, tested and put into operation by 31 March thanks to the intervention of the DSO e-distribuzione.
Simultaneously with the construction of the plant, an Energy Audit/Assessment was conducted on the entire Saico plant and on the related production process.
In the photos we show the installation of 434 Jinko Solar Tiger neo 565 Watt photovoltaic modules, a very large and powerful module that goes very well with the current industrial roofing.
The project is also realized thanks to the participation in the "Solar Attack" tender of the Umbria Region which, through European funding (PNRR), will allow the client to recover 40% of the expenses incurred.
Updates will follow at the end of the works from the Collepozzo plant!