Work progress Anodall Extrusion Spa: 3 MW photovoltaic system.
1059 modules installed in SECTION 4 and 504 modules in SECTION 2.
The construction activities of the 3 MW photovoltaic system for our client Anodall Extrusion S.p.A. are proceeding as scheduled, for which we have installed 1059 modules in SECTION 4 and 504 modules in SECTION 2.
(To find out when installation work has started, click on the following link)
We are talking about 570 watt JINKO SOLAR TIGER NEO modules, with N-TYPE monocrystalline silicon cells that maximize producibility performance.
To date, the total installed power is equal to 890.91 kW.
We specify that these first two sections of the plant will be connected to the national network in October, with the first partial entry into operation of the plant.
(Industrial roofing plant in Trevenzuolo VR)
(SECTION 4 view from above)
In the previous photo, you can also see the work on renovating the roofing (15,000 sqm) of the Anodall plant.
As of today, the ISOM SpA company has built one of the four spans with the prospect of completing the work by November.
In addition to the installation of the photovoltaic modules and related electrical connections (direct current), cabling work is underway (alternating current) which will power one of the customer's LV electrical panels.
As you can see from the photo below, we have already installed all the Growatt 125 KTL inverters: 20 machines, divided into 4 dedicated containers.
(Inverter room 1 of 4 boxes)
(4 Inverter Boxes in series)
The installation will continue in the coming weeks with a truly intense work program. In the months of October and November the system must be completed.
Our entire operational team is working on this system, made up of 4 employees for alternating current and 4 employees for direct current.
(Our frontline operations team)
Anyone interested in developing an industrial project that does not only concern the installation of photovoltaics, but which can be seen and extended at 360°: from the energy efficiency of the building envelope to specialized technical energy management consultancy, to the renovation of the roof and the related disposal of asbestos cement, the construction of the general plant systems including the systems dedicated to the production processes, you can send us an email, indicating the needs and the individual industrial requirements of your company's plant.
We will be happy to assist you by carrying out inspections and technical meetings aimed at drawing up an initial feasibility study completely free of charge.
Our technical team is always operational to meet the needs of future and new customers.